Multi-Discipline Power Project
- Client: Dee Why RSL
- Value: $ 1,750,000
- Project Type: Multi-Discipline Power Project
- Completed: September 2018
Connect was engaged by Dee Why RSL to design and construct a new power connection and substations to enable the future expansion of the club. The project involved two new kiosk substations, significant network augmentations including trenching and duct works, a new main switchboard, consumer mains and the decommissioning and removal of the old indoor substation.
All equipment had to meet Ausgrid standards. The diversity of work required a highly skilled and capable project team. Unlike many ASP L1 projects this project required a true multidiscipline approach. Connect's team were able to coordinate all skill sets and trades whilst ensuring the club's existing operations were not impacted.